Demolition

Decontamination/
Decommissioning


Site Remediation

Facility Infrastructure

  Demolition
   

Steel Manufacturing Plant - South-East
  • VIASANT crews demolished a 200’ tall furnace and other large structures at this DRI Plant utilizing conventional tripping of the structure.
  • An engineered controlled drop approach was used for secondary safety controls and to control the release of dust.
  • An earthen dike was placed along the impact zone to absorb the impact of the largest vessel.
    3,000 tons of steel was being removed and all scrap was prepared to a 3’ minus mill spec.
  • All castable and refractory brick was transported by VIASANT and placed in a designated area for temporary storage at the plant.
  • All construction and demolition debris, including 3,000 tons of waste, was transported and disposed off-site.